Home   About MARCO   More Information
Problems Explained
Pictures
Testimonials
Contact
Industrial
Chemical Grouting
Foundation Piering
Helix Anchor
Rock Fall Stabilization
Shotcrete/Gunite
Slabjacking
Slope Stabilization
Water Drainage
Magnum Piering
Residential Slope Stabilization

 This case study shows the absolute power of water especially when sufficient drainage measures have not been achieved.

Marco Concrete Lifting was originally contacted to give customer a "slabjacking" quote in order to raise driveway a few inches to the original elevation.  Continued movement prompted homeowner to confirm extent of problems before starting any work.  Within a few weeks, the entire driveway was forced down the slope by a major landside.  Geotechnical engineering reports showed just how unstable the land actually was.  The homeowner put a tremendous amount of effort into stabilizing the area enough to start the installation of the wire mesh/Magnum Helix retention system.  Over 230 tons of rock were placed at the based of the pool area, yet there was an ongoing battle to keep the soil stabilized.  A small break in the weather gave us the 2 days needed to install the wire mesh/Magnum Helix system.  Although we followed the engineering report completely, the design required additional helix anchors and wire mesh due to continued soil movement.  After several months of monitoring, the slope has finally reached a point of equilibrium.  Soil stabilization projects may be fairly straightforward or, as the following project shows, require significant effort to properly design and install a retention system. 


Although this home was built on stable
soil, surrounding property was at risk.

 


Slope of property is evident but the instability
materialized in the form of a landslide.

 


Natural fault line threatened rear
garage and pool area.

 


Pool area was located directly
above fault line.

 


Efforts to pull drain water away from
soil were ineffective.

 


View from previous spot of driveway.
Note angle of fallen trees.

 


Concrete slab is actually driveway
from above.

 


Driveway was completely lost to
landslide.

 


What was once a landscaped side yard
had now dropped over 6 feet.

 


Entire slope had migrated down
towards a natural creek bed.

 


An excavator with hydraulic torque
head is used to install anchors. 

 


Installation angles are maintained
to meet engineering report.

 


Helix Anchors may have one, two or
three helical blades. 

 


Pre-determined spacing between
anchors was very critical.  

 


8:30 pm and our crew is still on the job.
This job was very time sensative:  rain
could have jeopardized the whole project.

 


After Magnum Helix Anchors are installed,
wire mesh is laid and connected
using engineered compression claws.

 


 Spike Plates help distribute
pressure from shifting soil.


Over 4500 sq. ft. of wire mesh using
33 Magnum Helix Anchors. 
 

<Return to the Completed Projects page>

 

TOP OF PAGE
Magnum Piering Authorized Dealer
© Copyright 2004, Marco Concrete Lifting
Powered By: Enterprise Wizards